Johannesburg – Kumba Iron Ore says its flagship Sishen
mine improved production 31 percent year-on-year.
This, it says in a statement released on Monday, saw
production gain to 7.7 million tons thanks to increased plant throughput in the
three months to March.
The Anglo American company notes its export sales gained 7
percent to 10.1 million tons thanks to a 17 percent increase in total
production.
However, quarter-on-quarter, production dropped 10
percent as anticipated as the fourth quarter 2016 benefitted from greater
access to low strip ratio ore.
Waste removal of 34 million tons, in line with the first
quarter of 2016, was hampered by higher
than expected rainfall during the quarter, it says.
However, mining rates improved in the latter part of the
quarter to levels required to meet full year guidance of 150-160 million tons.
Kumba notes Kolomela production increased by 3 percent to
2.8 million tons year-on-year, driven by higher plant throughput.
Read also: Kumba CFO quits
However, production quarter-on-quarter was down 10
percent due to rain stoppages.
Waste mined at Kolomela increased by 32 percent to 10.1
million tons in support of production growth and ongoing improvements in operational
and mining efficiency.
Going forward, waste removal is expected to improve to
meet full year guidance for 2017 of 50-55 million tons.